On the quay in IJmuiden, two pink crane booms stand ready. Suspended between them is a cable reel as tall as a three-story building: 10.2 meters in diameter and weighing 92 tons. This is no standard cargo, this is precision work at the highest level.
ECL (Europe Caribbean Line) shipped this impressive subsea cable reel to Georgetown, Guyana. The TCP pipes on board will be used to connect wells deep below the seabed, essential infrastructure for the offshore industry.


A cargo of this size leaves no room for error. Loading a 10-meter-high, 92-ton cable reel requires perfect coordination between the office and the quay.
At ECL, lifting plans and weight calculations are meticulously prepared. But it is the captain and crew who bring these plans to life. Two cranes moving in perfect sync, a load finding its place centimeter by centimeter, and a team that knows concentration is the difference between success and standstill.
“With a 92-ton load rising 10 meters into the air, you don’t count seconds—you count millimeters. The calculations from the office were flawless. It’s then up to us to execute them on the quay. That moment when the reel is safely on deck—that’s what it’s all about.”
Captain, Vertom Joy
Once on board, the reel was carefully secured for the overseas journey. Additional security measures ensured this valuable cargo would safely cross the Atlantic Ocean.
This project demonstrates why clients with complex cargo choose ECL. Over 40 years of experience in project cargo to the Caribbean. Multipurpose vessels with heavy lifting capacity. And above all: a team that knows what it’s doing, from the drawing board to the quay.
Do you have a challenging project cargo? Contact us for a no-obligation quote.